Paralleling (Synchronising) Generators
Generator synchronization (paralleling): sync conditions, kW and kVAr load sharing, N+1 redundancy, grid paralleling and a comparison with a single set.

Contents
In facilities supplied by a single large generator, the set runs far below its capacity during low-load periods. For example, when a 1,400 kVA set runs at around 300 kVA on the night shift, oily soot forms in the exhaust, and the facility has no backup while the set is being serviced. If the same facility uses 3 × 700 kVA sets in parallel, a single set runs at low load, and during maintenance the other sets stand by as backup.
Synchronized (parallel) operation means two or more generators connected to the same busbar and supplying the load together. Generators can run in parallel with each other or with the grid. The condition is this: the voltage, frequency, phase sequence and phase angle of the incoming set must match those on the busbar. Once connected, active and reactive power must be shared evenly between the sets. This job is done by the synchronization panel and the generator control units.
Synchronization conditions
| Parameter | Why does it matter? | Typical window (approximate, adjustable) |
|---|---|---|
| Phase sequence | Connecting in the wrong sequence causes serious damage | Must be the same (L1-L2-L3) |
| Voltage | A difference produces a reactive balancing current | A few % |
| Frequency | A difference creates a power surge at the moment of connection | ~0.1–0.2 Hz |
| Phase angle | A large difference creates a mechanical and electrical shock | ~±10° |
The control unit adjusts the speed and voltage of the incoming set to bring the values closer. When the conditions are met, it closes the breaker. If the busbar is empty (dead bus), the first set ready connects directly; the others synchronize to it. Interlocking logic that prevents two sets from closing onto a dead bus at the same time is essential.
Load sharing
- Active power (kW): Shared by the speed governors. In modern systems the control units communicate with each other; frequency stays constant and the load is distributed in proportion to the sets’ ratings (isochronous load sharing). The other method is droop: speed drops slightly as load increases, and the sets share the load accordingly.
- Reactive power (kVAr): Shared by the AVRs. If reactive sharing is off, circulating current flows between the sets. One set shows high current while another shows low; the alternators heat up for nothing.
Load sharing is never perfect. When calculating total capacity, leaving a margin of a few per cent is common practice. The exact values are in the control system manufacturer’s data.
Why parallel?
- Redundancy (N+1): Even if one set fails or goes in for maintenance, the rest carry the load.
- Running to suit the load: When the load drops, unneeded sets stop automatically. The remaining sets run in their efficient range, and problems caused by low load (wet stacking) are reduced.
- Step-by-step growth: New sets are added as the facility grows.
- Easier maintenance: Sets are taken out for maintenance one at a time.
- High power: Requirements that exceed the rating of a single set are met with several sets; for very large systems, medium voltage solutions are also considered.
There is a price too: more panels, more complex control, more space and usually a higher initial investment.
One large set or parallel sets?
Example: 1,200 kVA critical load.
| Option | Installed power | With one set out of service | Note |
|---|---|---|---|
| 1 × 1,400 kVA | 1,400 kVA | 0 kVA | Simple, no redundancy |
| 2 × 1,400 kVA (1+1) | 2,800 kVA | 1,400 kVA | Fully redundant, high installed power |
| 3 × 700 kVA (N+1) | 2,100 kVA | 1,400 kVA | Redundant, step-by-step running |
The figures are there to illustrate the method. In a real selection, the power rating (standby, prime, continuous), load steps, motor starts and layout are assessed together.
Paralleling with the grid
Typical applications:
- Closed transition: Transferring the load without interruption when the mains returns.
- Peak shaving: Limiting the power drawn from the grid during expensive hours.
- Continuous parallel operation: For example, cogeneration.
Grid paralleling requires reverse power, loss-of-mains (such as vector shift and ROCOF) and synchronization protection. The connection is usually subject to the distribution company’s permission and technical requirements.
Common mistakes on site
- Alternators with different winding pitches. If alternators running in parallel have different winding pitches (e.g. 2/3 pitch), third-harmonic current can circulate through the neutral. The neutral cable heats up.
- Neutral earthing is thought about set by set. A separate neutral–earth link on each set can lead to circulating currents. See generator earthing.
- Communication line failure is not defined. Nobody knows what the system will do if the cable between the control units breaks.
- No load shedding. When one set drops out, the rest are overloaded and a chain of shutdowns follows. Priority loads and load shedding logic must be defined from the start.
- The real scenario is not tried during commissioning. Synchronization, load sharing, loss of a set and load steps should be tested with the real load or a load bank; see load bank testing.
Checklist
- Are the total load, load steps and redundancy target (N, N+1, 2N) known?
- With one set out of service, can the rest meet the load?
- Are the control units and speed governors suitable for parallel operation?
- Are the alternator types and winding pitches compatible?
- Has the neutral–earth arrangement been designed at system level?
- If there is grid paralleling, have the distribution company’s requirements and the protection been defined?
- Are the load shedding and priority logic written down?
- Were synchronization and load sharing tested during commissioning?
Next step
Parallel systems are used most in data centres, hospitals and industrial facilities. To assess the generator and synchronization panel arrangement for your project with the Terex Diesel team, contact us.
Planning a generator for a project?
Send us the power, voltage and destination. We reply with a suitable model, the factory price and the lead time within 24 hours on working days.
Frequently asked questions
What conditions are needed to run generators in parallel?
For a generator to connect to the busbar, its voltage, frequency, phase sequence and phase angle must match those on the busbar. The synchronization control unit measures these values and closes the breaker when the differences fall within the set limits. Once connected, active power (kW) is shared by the speed governors and reactive power (kVAr) by the AVRs.
Can generators of different ratings run in parallel?
Yes, with a suitable control system, generators of different ratings can run in parallel; the load is shared in proportion to each set's rating. However, the alternators' winding pitch, neutral connection, dynamic behaviour and the compatibility of the control units should be assessed separately in the design.
One large generator or several generators in parallel?
A single large set means less space, simpler control and usually a lower initial investment. Sets running in parallel offer redundancy (N+1), step-by-step growth, efficient running at low load and maintenance without interruption. In critical facilities and with variable loads, a parallel system usually comes out ahead.
Featured models
Technical data of models in frequently requested power ratings:
- 38 kVATRX QZ TA 0038Quartz Q490ZD
- 58 kVATRX QZ TA 0058Quartz Q4105D
- 77 kVATRX QZ TA 0077Quartz Q4105ZD
- 105 kVATRX QZ TA 0105Quartz Q4105AZLD
- 155 kVATRX QZ TA 0155Quartz Q6105AZLD
- 260 kVATRX SD TA 0260SDEC SC9D310D2
- 300 kVATRX SD TA 0300SDEC SC9D340D2
- 400 kVATRX SD TA 0400SDEC SC15G500D2
- 520 kVATRX SD TA 0520SDEC SC25G610D2
Related articles

Generator Room and Installation
Generator room ventilation and installation guide: radiator air discharge, exhaust line and back pressure, fuel, concrete plinth, vibration and earthing.

What Is an ATS? Automatic Transfer Switch
What is an ATS and how does it work? Transfer sequence, delay times, 3- or 4-pole choice, current calculation (kVA × 1.44) and a checklist.

Using a UPS with a Generator
For a 200 kVA UPS with an IGBT rectifier, plan about 250–300 kVA of generator; an older 6-pulse UPS may need twice that. Harmonics and frequency.

Generator Earthing (Grounding)
How is a generator earthed? Protective and system earthing, TN and TT systems, the neutral–earth link, ATS pole count and resistance measurement.

Remote Generator Monitoring
How does generator remote monitoring work? Controller, GSM/4G, Ethernet, Modbus, what values to monitor, alarm settings and cyber security.

Generator Exhaust Systems: Piping, Silencers and Back Pressure
How to design a generator exhaust line: pipe diameter, bends and length, back pressure limit, silencer grades, flexible connector, insulation and outlet.